Days 61–90 in the Field: Learn to Anticipate the Work

By Clyde Pershall · FieldWise Training™

During the first 30 days, a new field employee learns the project.

During days 31 through 60, they begin following the work.

During days 61 through 90, they should begin anticipating it.

This does not mean an employee with three months of experience is ready to manage an entire project. It means they should start looking beyond the activity directly in front of them and asking what must happen next.

That change—from reporting what happened to preparing for what is about to happen—is an important step toward field leadership.

Progress Is Only Part of the Story

We often spend meetings asking subcontractors to report progress.

But progress can be seen by walking the project.

The more valuable questions are:

A field leader must understand today’s progress, but the greater responsibility is preparing tomorrow’s work.

Teach developing employees to look ahead far enough to recognize a problem while there is still time to solve it.

Looking Ahead Is Not Guessing

Anticipation should be based on information.

The employee should use the drawings, specifications, approved submittals, project schedule, short-term plan, procurement information, field conditions, and conversations with subcontractors.

Before an activity begins, they should ask:

These questions turn a schedule activity into a workable field plan.

Test the Plan in the Field

A plan that only works on paper is not a field plan.

Walk the area where the activity will occur. Check access, elevations, dimensions, existing conditions, stored materials, temporary protection, equipment routes, overhead work, and nearby trades.

Compare the plan with what is actually in place.

A drawing may indicate that work can begin, while the field shows that an earlier activity is incomplete. The schedule may show available space, while materials or equipment have blocked access.

Teach the employee to test information against field conditions.

The documents tell us what should happen. The field tells us whether the project is ready for it to happen.

Give Them a Limited Look-Ahead

During days 61 through 90, give the employee responsibility for a limited portion of the look-ahead plan.

This might involve one subcontractor, one area, or one clearly defined sequence.

Ask them to identify:

  1. The work planned during the next two or three weeks.
  2. The information, materials, manpower, equipment, inspections, and access required.
  3. The preceding work that must be complete.
  4. The decisions that remain unresolved.
  5. The trades affected by the activity.
  6. The date each constraint must be cleared.

Then ask them to walk the field and speak with the people performing the work.

The employee should be able to explain not only what is scheduled, but also whether it is ready and what must be done to keep it moving.

Teach Escalation, Not Silence

New employees sometimes notice a problem but hesitate to speak because they are unsure whether it is important.

Teach them how and when to escalate a concern.

A good escalation should explain:

They do not need to know the final answer before raising the question.

Waiting until they are certain can mean waiting until the problem has already affected the work.

The objective is to communicate early enough for the team to act.

Move From Instructions to Questions

During the first few weeks, an experienced leader may need to provide direct instructions.

As the employee develops, the conversation should change.

Instead of always saying, “Here is what you need to do,” ask:

These questions require the employee to organize information and explain their reasoning.

That process helps build judgment.

Review the Entire 90 Days

At the end of 90 days, sit down with the employee and review their progress.

Discuss what they have learned about the project, where they have accepted responsibility, and where they still need development.

The review should include:

The purpose is not simply to assign a rating. It is to establish the next stage of development.

A structured first 90 days should lead into continued coaching, broader responsibility, and practical field training.

The Goal Is a Way of Thinking

After 90 days, an employee will not know everything about construction.

None of us do.

But they should be developing a reliable way to approach the work. They should know how to find information, observe field conditions, follow an activity, recognize constraints, ask better questions, and communicate before a problem grows.

That is the real objective.

We are not trying to give new employees every answer. We are teaching them how to think through the work.

FieldWise Training™ helps bridge the gap between education and real construction-field experience. Drawing on more than 40 years in construction, we pass practical field knowledge to the next generation.

We’ll teach you how to think, not what to think.